Using a Subcontractor for Installation

Set-up a Part with Subcontractor Costs for Installation

Last Updated By Michael Croteau

Updated at December 16th, 2022

Set-up a Part with Subcontractor Costs for Installation

In this example, we'll take a look at how you can create a part that includes Material Cost for materials, but uses a Subcontractor for the installation cost.

Simple Steps

  1. From your Projects page, open your part with the pencil button (far right).
  2. Un-check the "Labor Cost Calculation" box to remove the Labor Cost
  3. Check the "Subcontractor Cost Calculation" box to include Subcontractor Cost for installation
  4. Change "Subcontractor Cost Calculation" to "$/unit"
  5. Enter the dollar amount per unit for installation

     

Example

For this example, we'll assume $10.00/sq ft for Material cost, and $5.00/sq ft for Subcontractor installation:

 